THE OPPORTUNITY
The base building’s existing steam absorption chillers, that provide the large tonnage central air conditioning, had served beyond its useful life and needed to be replaced. After consideration of all the factors, the client opted to replace their existing absorbers with new electric chillers. Electric chillers offer a number of key benefits.
- A higher COP (Coefficient of Performance)
- lower equipment purchase cost
- A 50% savings in required floorspace
- Shorter installation time
- Overall reduced energy consumption for added cost savings
THE PROJECT
Donnelly handled the project planning, 3D modeling, and management. The existing steam absorption chillers on the 13th floor were removed, and two new chillers were hoisted via crane. New critical electric equipment was installed to power the new chillers. 3 A/C units were installed to cool critical electrical equipment on the 61st and 63rd floors.
THE OUTCOME
Having provided accurate estimates, Donnelly completed the project on-time and within budget. Donnelly’s Building Information Modeling (BIM) capabilities and strategic alliance with Elite CAD Designs facilitated detailed 3D modeling to ensure successful project planning and logistics. Donnelly’s expert project management and attention to safety kept workers and equipment safe throughout this challenging installation project.
– Chief Engineer at Boston Properties