Electric Chillers Installation in Corporate High-Rise

THE OPPORTUNITY

The base building’s existing steam absorption chillers, that provide the large tonnage central air conditioning, had served beyond its useful life and needed to be replaced. After consideration of all the factors, the client opted to replace their existing absorbers with new electric chillers. Electric chillers offer a number of key benefits such as higher COP (Coefficient of Performance), lower equipment purchase cost, a 50% savings in required floorspace, shorter installation time, and overall reduced energy consumption for added cost savings.

THE PROJECT

Donnelly handled the project planning, 3D modelling, and management. The existing steam absorption chillers on the 13th floor were removed, and two new chillers were hoisted via crane. New critical electric equipment was installed to power the new chillers. 3 A/C units were installed to cool critical electrical equipment on the 61st and 63rd floors.

THE OUTCOME

Having provided accurate estimates, Donnelly completed the project on-time and within budget. Donnelly’s BIM capabilities and strategic alliance with Elite CAD Designs facilitated detailed 3D modelling to ensure successful project planning and logistics. Donnelly’s expert project management and attention to safety kept workers and equipment safe throughout this challenging installation project.

We really appreciate Donnelly’s expert project management and attention to the details, including managing the rigging that lifted the 900-ton and 2050-ton chillers from the truck up to the 13th floor through the curtain wall. It’s difficult to do a project of this size without any issues.

Chief Engineer at Boston Properties

Back to Featured Projects